Contacts
Get in touch
Close

Contacts

Romania, Cluj-Napoca – 400157
Str. Ploiești Nr. 9

Romania, Vama – 447350
Str. Fermei Nr. 14

+40 774 463 429

info@inteliscience.net

Cost Estimation from Past Projects: An ETO Quoting Guide

Cost Estimation from Past Projects: The Short Version

Cost estimation from past projects prices a new engineer-to-order RFQ from the actual costs of technically similar completed projects, then adjusts for what differs. inteliScience builds AI that finds those comparables, explains why each one matches, cites the source documents and links them read-only to ERP cost and procurement data. Estimators start from evidence and keep every pricing decision.


The Problem: The Best Cost Data Sits in Projects Nobody Can Find

Every engineer-to-order company already owns the best estimating database it will ever have: its own completed projects. The trouble is access. The specification of a machine delivered years ago lies on a file server, its structure in the PDM system, its actual costs in the ERP post-calculation, and the lessons learned in a wiki or in one senior estimator’s head.

So the comparable project gets found by memory.

When the person who remembers it is on holiday, the quote starts from a blank sheet or from whichever project happens to be open, and a loosely similar project lends the estimate a false sense of grounding.

Forecasting research names the underlying problem. Bent Flyvbjerg traced inaccurate project cost forecasts to optimism bias and strategic misrepresentation, and proposed reference class forecasting as the remedy: base the forecast on the actual outcomes of a class of comparable projects, not on the inside view of the one in front of you. Cost estimation from past projects is that idea applied to a quotation desk.

The market adds pressure. On 17 September 2026 the German engineering association VDMA said it expects machinery production to shrink by 2 percent in real terms in 2026, which would be the fourth year of decline in a row, with growth of 3 percent expected only for 2027. With fewer orders around, a quote priced too high loses the job, and one priced too low wins a loss.

Analogous, Parametric or Bottom-Up: Which Estimating Method Fits ETO

All three methods are established, and they answer different questions. The PMI Lexicon of Project Management Terms (Version 5.0, January 2026) defines analogous estimating as estimating cost or duration from historical data of a similar activity or project, parametric estimating as an algorithm that calculates cost from historical data and project parameters, and bottom-up estimating as aggregating the estimates of lower-level work breakdown components.

Method What it needs Where it fits in ETO quoting Main weakness
Analogous (top-down)One or more truly comparable completed projects with actual costsEarly RFQ stage, budget quotes, plausibility check of a detailed quoteOnly as good as the comparable; unnoticed differences slip through
ParametricEnough similar projects to fit a cost relationship, for example cost per axis or per stationProduct families with repeating modules and stable cost driversBreaks on one-off designs and needs a clean, uniform history
Bottom-upA bill of materials and routing, or at least a module structure with quantitiesDetailed quotes and the modules that are genuinely newSlow, and at RFQ stage the design rarely exists yet
Reference class forecastingOutcomes of a whole class of comparable projects, overruns includedContingency and a sanity check against optimismNeeds honest post-calculations, including the painful ones

What AACE’s estimate classes say about comparables

AACE International, the professional association for cost engineering, ties the estimating method to how mature the project definition is. In its matrix, a Class 5 estimate (0 to 2 percent of the definition complete) uses capacity factoring, parametric models, judgment or analogy, with typical accuracy ranges of minus 20 to minus 50 percent on the low side and plus 30 to plus 100 percent on the high side. These figures come from the process-plant addendum 18R-97, which explicitly excludes assembly and manufacturing, so read them as an illustration of how wide early estimates are, not as a benchmark for machines.

Two details matter more for ETO than the ranges. First, AACE lists bid or tender as the end usage of Classes 2 and 1, with 30 to 100 percent of the definition complete, yet an ETO quote is a binding offer written long before the machine is designed. Second, AACE’s recommended practices note that a Class 5 estimate based on a repeat project with good cost history and data can be as accurate as a Class 3 estimate for a project involving new technology. A good comparable is worth a lot of project definition.

Our position: for ETO, use analogous estimating for the whole machine and bottom-up only for the delta. Pure bottom-up at RFQ stage means estimating a design that does not exist yet; pure analogy means pricing differences nobody noticed. That hybrid is how experienced estimators already work; AI makes the analogy step reliable instead of dependent on memory.

How AI Finds the Comparable Projects

AI finds comparable projects by reading the incoming RFQ the way an estimator would, then searching completed projects for the same technical requirements rather than the same keywords. The output is not a price but a ranked list of past projects, each with the reason it was rated similar and the documents behind it.

The workflow we implement at inteliScience, an engineering data and Siemens NX specialist that works CAD-neutral, has four steps:

  1. Read the whole RFQ package. The requirements specification, technical PDFs, drawings and further requirements are analyzed together, not file by file.
  2. Recognize what drives cost. The AI extracts the relevant technical requirements and features, such as the handling task, payloads, cycle times, safety requirements and the acceptance conditions the customer prescribes.
  3. Search completed projects. Those requirements are matched against the specifications, PDM records and documentation of finished projects.
  4. Explain every hit. For each similar project it shows why it was rated similar, which documents and information exist for it, and the direct source passages.

Turning a long specification into a clean, sourced requirements list is a topic of its own, covered in our article on AI analysis of requirements specifications.

For this document- and metadata-based search, the CAD system does not need to be connected: part and assembly numbers, names, structure and project assignment come from the PDM, commercial or built in-house on a SQL database, whether your designers work in Siemens NX, CATIA, SolidWorks or Creo. Geometry-based part similarity is a separate technique with its own one-time index over the part library. It helps with part reuse, but it does not read a specification and does not know what a project cost.

Linking Comparables to ERP Cost, Procurement and Quotation Data

A similar project only helps a quote once its numbers are attached. We link each hit to its PDM record and to ERP data (article master, actual costs, purchase prices, suppliers, lead times, the original quotation), read-only through the standard interfaces of an ERP such as SAP Business One, SAP S/4HANA or Proalpha. We do not write into the ERP and do not replace it.

The harder question is which number from the past project to trust. An ETO project leaves at least three different cost figures behind, and they disagree for good reasons.

Figure from the past project Where it lives What it tells the estimator Trap
Original quotation priceERP sales documentsWhat the market accepted at the timeRepeats the old assumptions, including the wrong ones
Pre-calculationERP or estimating spreadsheetsWhat the team expected the job to costCarries the optimism of the bid phase
Post-calculation (actual costs)ERP order or project costingWhat the job really cost, by cost groupOnly complete if all hours were booked to the order
Purchase prices and lead timesERP purchasingSupplier, price level and delivery time of key componentsPrice level and supplier may no longer be valid

Our clear recommendation: anchor on the post-calculation, and read the gap between pre-calculation and actuals as the most useful piece of information in the archive. That gap is your reference class telling you where your estimates drift.

All of this depends on a project or order number that runs consistently through PDM, ERP, wiki and file server. If it does, linking is simple; if not, it is still solvable, but it becomes part of the project, which is why we check this first. How to establish that thread without replacing either system is the subject of our guide to connecting PDM and ERP through one project number.

A spreadsheet of past projects and one good memory are the POC. What production quoting needs: one project number across PDM and ERP, read-only access through standard interfaces, a cited source behind every hit, and access rights that mirror your source systems. We build that as one service: similar project search for incoming RFQs.

From Comparable to Estimate: Normalize First, Then Re-Estimate the Delta

A comparable project’s actual cost is not today’s price. Before it can anchor a quote, each cost group is brought to today’s price level, and groups where the new scope differs are replaced by fresh bottom-up numbers. The arithmetic is simple; the discipline lies in doing it per cost group, because labor, steel and electrical components rarely move together.

def adjust_reference(actuals, index_then, index_now, deltas):
    """Turn one comparable project's post-calculation into a starting estimate.

    actuals    : cost group -> actual cost from the ERP post-calculation
    index_then : cost group -> price index at the comparable's cost date
    index_now  : cost group -> the same index today
    deltas     : cost group -> fresh bottom-up estimate where the scope differs
    """
    adjusted = {
        group: cost * index_now[group] / index_then[group]
        for group, cost in actuals.items()
    }
    adjusted.update(deltas)  # the estimator's numbers win where the scope changed
    return adjusted, sum(adjusted.values())

Choosing the index and deciding what counts as changed stay estimator decisions; the function only makes them explicit.

Checklist: before you trust a comparable

  1. Scope: did the old project include installation, training or spare parts that the new RFQ does not, or vice versa?
  2. Completeness: were engineering, commissioning and warranty hours booked to the order, or to an overhead cost center?
  3. Price level: when were the costs incurred, and which index applies to each cost group?
  4. Sourcing: were key components bought from a supplier or in a currency you no longer use?
  5. Outcome: did the project end on budget? A comparable that overran is still useful, as a warning.
  6. Customer requirements: other standards, documentation depth or acceptance tests can move cost more than the hardware.

Showing Sources: Every Number in the Quote Needs a Trail

A cost estimate from past projects is only as defensible as its trail: every figure the estimator takes over should point back to its project, its ERP record and the specification passage that made the project comparable. Without that trail, an AI suggestion is an opinion, and nobody should sign a binding offer on an opinion.

On screen, that means three things per hit: the similarity reasons in plain language, the cited passages from the old and new specification side by side, and the linked ERP records with their dates. Citations must also respect permissions: an estimator only sees passages from documents they may open in the source system. We have run this kind of traceable retrieval over confidential documents in production, in a private RAG knowledge assistant on internal company documents.

We’d advise against any tool that outputs a price without the projects behind it. A single number hides whether it came from three close matches or from one loose one, and the estimator cannot tell the difference. There is also a practical argument. An ETO project history is rarely large or uniform enough to train a reliable price model, but it is always large enough to search.

Where Human Judgment Stays

The AI prepares the evidence; estimators and sales decide the price. That split is not a temporary limitation of today’s models. A project archive simply cannot know the customer relationship, the competitive situation or the state of your shop floor next spring.

The AI prepares The estimator decides
Ranked comparable projects with reasonsWhether the similarity holds for this customer and this site
Cited passages from old and new specificationsWhich differences matter, and what they cost
Actual costs, purchase prices and lead times from the ERPEscalation, currency and commodity risk
Notes on overruns and rework in the comparablesRisk premium and contingency
Original quotation and post-calculation side by sideMargin, strategic pricing, bid or no-bid

Reference class forecasting is a useful discipline here. Look at how the comparable projects actually ended, overruns included, before you adjust for “this time is different”. Flyvbjerg’s point is that the inside view of a single project tends to be more optimistic than the record of its peers.

Where this ends and a DFM check begins

Cost estimation from past projects works at project level: what did a comparable machine or line actually cost, and what did we buy for it? If most of your RFQs are parts or assemblies to customer print and the first question is whether your shop can make them at margin, that is a different workflow, covered by our AI DFM and quotation check for machine builders. Both can draw on the same project and part history.


Frequently Asked Questions

What is cost estimation from past projects?

Cost estimation from past projects is analogous estimating: a new project is priced from the actual costs of similar completed projects, adjusted for the differences. In engineer-to-order quoting it means using post-calculations, purchase prices and original quotations of technically comparable machines from the ERP. inteliScience builds AI that finds those comparables from the RFQ documents and cites the sources for every match.

How accurate is analogous estimating compared with bottom-up estimating?

It depends more on the quality of the comparable than on the method. AACE International lists analogy among Class 5 methods, with typical ranges of minus 20 to minus 50 and plus 30 to plus 100 percent for process plants, while detailed bottom-up estimating belongs to Classes 2 and 1. Yet AACE also notes that an estimate based on a repeat project with good cost history can match a Class 3 estimate for new technology.

Can AI estimate the cost of an engineer-to-order machine?

AI can prepare an ETO cost estimate, but it should not set the price on its own. Its strength is finding technically similar completed projects, explaining why they match and attaching their actual costs from the ERP. The estimator then prices the differences and decides risk and margin, because a price predicted without visible comparables is hard to check and hard to defend.

How much does it cost to set up AI cost estimation from historical project data?

There is no fixed figure: the effort depends mainly on the quality and linkability of the existing data, not on the AI. If one project or order number runs consistently through PDM, ERP, wiki and file server, linking is straightforward; if not, establishing that link becomes part of the project. A bounded proof of concept on one product family and a handful of completed projects yields a reliable effort estimate.

Which ERP data is needed for cost estimation from past projects?

The essentials are actual costs per order from the post-calculation, the article master, purchase prices with suppliers and lead times, and the original quotation. All of it can be read, read-only, through the ERP vendor’s standard interfaces. Hours booked per order matter as much as material costs, because engineering and commissioning effort is the part hardest to derive from a specification alone.


Next Step

Pick one recent RFQ and the past project you would have compared it with. In a strategy call, our engineers, delivering nearshore from Romania, check whether your project numbers connect PDM and ERP and scope a Quick Scan with an on-site workshop, followed by an NX Sprint on one product family and a handful of completed projects. Both steps are part of our engineering data AI services, which inteliScience delivers from one hand.

Book a strategy call about quoting from your project history



Sources

Cookie settings

Choose which services we may use on this website. Your choice is stored in your browser for 12 months. You can change it at any time via “Cookie settings” at the bottom of every page.

Strictly necessary

Stores your cookie choice. This cookie cannot be switched off.

Always active
Show cookies
NameProviderPurposeStorage period
is_cookie_consentinteliScienceStores your cookie choice and when you made it12 months

Google Analytics 4 measures page views, traffic sources and form use with a pseudonymous ID. Provider: Google Ireland Ltd. Data may also be processed by Google LLC in the USA (EU–US Data Privacy Framework).

Show cookies
NameProviderPurposeStorage period
_gaGoogleDistinguishes visitors with a pseudonymous ID2 years
_ga_<ID>GoogleStores the session state2 years

Google Ads measures which ads lead to enquiries (conversions) and lets us show our ads to previous visitors (remarketing). Provider: Google Ireland Ltd. Data may also be processed by Google LLC in the USA (EU–US Data Privacy Framework).

Show cookies
NameProviderPurposeStorage period
_gcl_au, _gcl_aw, _gcl_gsGoogleLinks ad clicks to enquiries90 days
_gcl_ls (local storage)GoogleLinks ad clicks to enquiries90 days
IDE (doubleclick.net)GoogleRemarketing and ad measurement13 months

Videos: YouTube videos only load when you press play (via youtube-nocookie.com). Only then does Google receive data.